Go Back   The Supercar Registry > General Discussion > Technical & Restoration


Reply
 
Thread Tools Display Modes
  #1  
Old 04-09-2018, 07:12 PM
Krateness Krateness is offline
Yenko Contributing Member
 
Join Date: Jul 2017
Posts: 48
Thanks: 0
Thanked 16 Times in 6 Posts
Default

Thanks guys.

Cars a Copo car built with a body tag build date of the 1st week of July.

For the stuff the car isn’t missing, most of it is dated in May so May/June is probably the right window I should be looking for.
Reply With Quote
  #2  
Old 04-11-2018, 12:35 AM
m22mike's Avatar
m22mike m22mike is offline
Senior Member
 
Join Date: Jan 2006
Location: West of CAK
Posts: 5,001
Thanks: 766
Thanked 840 Times in 406 Posts
Default

Quote:
Originally Posted by Krateness View Post
Thanks guys.

Cars a Copo car built with a body tag build date of the 1st week of July.

For the stuff the car isn’t missing, most of it is dated in May so May/June is probably the right window I should be looking for.
Have you looked at your vin # for a better idea of when it was actually built ? Compare your's with the vin totals for July .
Being a COPO It may have spent time in the body bank waiting to be scheduled. That could make the assy weeks ? Later than the TT date.
Date codes are not always X amount of time ahead of assembly. The driver mirror on my Malibu is 6 mo. ahead of assy.

Mike
Reply With Quote
  #3  
Old 04-11-2018, 01:16 AM
Krateness Krateness is offline
Yenko Contributing Member
 
Join Date: Jul 2017
Posts: 48
Thanks: 0
Thanked 16 Times in 6 Posts
Default

Quote:
Originally Posted by m22mike View Post
Have you looked at your vin # for a better idea of when it was actually built ? Compare your's with the vin totals for July .
Being a COPO It may have spent time in the body bank waiting to be scheduled. That could make the assy weeks ? Later than the TT date.
Date codes are not always X amount of time ahead of assembly. The driver mirror on my Malibu is 6 mo. ahead of assy.

Mike
In all honesty the car is more than just a COPO but is actually the fathom green Yenko found in Indiana last year. I’m helping in trying to track down what pieces the car is missing. NCRS documents showed an official production date of 7/10/69 before being shipped off to Yenko.

I have a friend who has a 944 (April/ 4th Week / 1969) 4346 carb and before setting out and buying one, if this one would technically be correct for the date code I’d just roll with it.
Reply With Quote
  #4  
Old 04-11-2018, 02:29 AM
6667ss138 6667ss138 is offline
Yenko Contributing Member
 
Join Date: Apr 2017
Posts: 192
Thanks: 20
Thanked 68 Times in 29 Posts
Default

Quote:
Originally Posted by Krateness View Post
In all honesty the car is more than just a COPO but is actually the fathom green Yenko found in Indiana last year. I’m helping in trying to track down what pieces the car is missing. NCRS documents showed an official production date of 7/10/69 before being shipped off to Yenko.

I have a friend who has a 944 (April/ 4th Week / 1969) 4346 carb and before setting out and buying one, if this one would technically be correct for the date code I’d just roll with it.
Your COPO official production date has the same exact date as my X77 HO Z/28 (07A July 10th) according to my NCRS report. I have a lot of original born with assembly line parts still on the car and many are dated May. My 302 engine assembly date, heads, distributor, alternator, and carb for example are all May. The Muncie and BU rear are June. I think April would not be out of the question as they were about to wind down for the one month shutdown and were using up all available left over inventory. July 11th was the last day of production before the one month shutdown. I hope this helps.

Last edited by 6667ss138; 04-11-2018 at 02:36 AM.
Reply With Quote
  #5  
Old 04-11-2018, 04:14 PM
Kurt S Kurt S is offline
Yenko Contributing Member
 
Join Date: Aug 2000
Location: Ann Arbor, MI
Posts: 3,086
Thanks: 2
Thanked 781 Times in 363 Posts
Default

Quote:
Originally Posted by m22mike View Post
Being a COPO It may have spent time in the body bank waiting to be scheduled. That could make the assy weeks ? Later than the TT date.
That's not how the body bank worked. All 6 of the lines in the body bank were always feeding the main line. A given car left the bank within minutes, not hours, of arriving.
http://www.camaros.org/assemblyprocess.shtml#chev
"There were usually six lines in the schedule bank - one for RS, one for A/C, one for SS and Z/28, and three for high-volume standard cars, so cars could be scheduled without having situations like three A/C's in a row, three consoles in a row, three RS's in a row, etc., as these had higher work content vs. the standard cars and scheduling two or three of them in a row would over-cycle certain line operations."
__________________
Kurt S - CRG
Reply With Quote
The Following User Says Thank You to Kurt S For This Useful Post:
m22mike (04-11-2018)
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Forum Jump


All times are GMT. The time now is 12:55 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.

O Garage vBulletin Plugins by Drive Thru Online, Inc.